Posts

Showing posts from January, 2024

LATEST PICTURES OF TOILET REPAIR

Image
The latest pictures of the repair of toilets near Masjid Matar in Markaz Ahlie.  new toilet bowls are installed new doors are going to be installed the ceiling is raised the septic tank behind the toilet is given concrete finish

TOILET (MASJID MATAR) REPAIR HAS BEGUN

Image
The materials for the repair of the 4-door toilets of Masjid Matar have arrived at the Markaz. The construction has already started.

LATEST PROGRESS OF ONGOING REPAIR OF MASJID MATAR

Image
1) New roof and ceiling replaced the old ones. The plywood ceiling were painted to increase durability 2) The painting of the interior and exterior of the masjid as well as the fence was completed. 3) Two new doors were installed which replaced the old ones.

ONGOING REPAIR OF MASJID MATAR

Image
 The repair started late December 2023. The priorities were replacing the roof and ceilings with new ones including the timber frames.